| What is the Health of My Project? The Use and Benefits of Earned Value - Page 3 |
|
|
Page 3 of 4
To Complete Performance IndexThe To Complete Performance Index (TCPI) is an index that rates the probability of a forecast. It is also known as the CPI to EAC index. This index is used to gain confidence in the reported estimate for the remaining work. A forecast is probable if the TCPI equals one. Do I have the necessary staff for this new contract?Full Time Equivalents (FTE), or equivalent staffing units, are commonly used instead of hours to project staffing requirements. The number of working hours per month should include a productivity factor to determine accurate staffing requirements. The productivity factor might be different for various personnel, locations, and times of year. Along with productivity factors based on the season and personnel, there are also efficiency factors dependent on past performance that can be applied to the staffing requirement for the remaining work. If the staffing requirements for a project have been overrunning to date, using the baseline plan from the current time to completion implies an expectation that staffing performance will improve. When analyzing staffing requirements you need to make sure that all activities, including level of effort activities, are considered. You need to provide for different productivity rates per resource and per month in order to determine an accurate staffing requirement based on the hours required to complete a project. Will labor rate and currency exchange rate fluctuations affect my project's cost?Rate fluctuations will affect the final project cost. Since cost of living adjustments are difficult to predict, it is helpful to have all rate escalations defined in a single rate set. This way you can define all labor rates as today's rate and change the labor rate escalation for all resources in a single place. This type of rate analysis can also be beneficial when dealing with currency exchange rates. By using multiple "what-if" scenarios, a good EVM software package can easily and effectively allow you to analyze the effects of all types of challenges presented to today's project managers. How will funding cuts affect my cash flow?When analyzing a project, it is important that you are able to compare budget, actual costs, and funding.
Figure 5 shows how the actual costs reflect the funding. What is causing my cost variance?Many conditions cause cost variances. You need to ask yourself if your project is taking more resources to do the work than you originally planned or if the resources are more expensive than planned. To accomplish this analysis, you compare the earned rate to the actual rate and the budgeted hours to the actual hours. The derived costs associated with earned value are not calculated using a rate file but by earning the budget hours and associated derived costs. Therefore, the earned value rate and the budgeted rate are most likely the same. However, when you examine variances, you should be analyzing earned versus actual as opposed to budgeted versus actual. For example, you might earn 100 hours and there are 100 actual hours. If your actual cost is much higher than the earned value, then you have a rate variance as opposed to an efficiency variance. The rate variance is calculated using the following formula:
To calculate an earned rate, the following formula is used: An actual rate is calculated by looking at the posted quantities:
A positive rate variance indicates that the actual rate is less than the earned rate. Rate variances are compensated for in a forecast by changing the to-go labor rate for your forecast. If you are given an estimate to complete (ETC), the to-go labor rate is compared with the budgeted rate by calculating the to-go labor rate as follows: In addition to rate variance, there is an efficiency variance. An example of an efficiency variance is when you budget and earn 100 hours, but there are 120 actual hours. An efficiency variance is compensated for in a forecast by using statistical forecast methods based on previous performance. Multiplying the remaining effort by 1/(CPI*SPI) is a good means of projecting the final cost. Efficiency variance is calculated as follows: Any time that a cost variance is incurred during a project, it is important to determine what is causing the variance. Is it a rate variance or an efficiency variance? In addition to simply changing the final project cost, the work being performed should be investigated to see if there are any means of improving the situation. Earned value gives you the early warning you need to solve problems while the work is in progress before the actual costs are above the total budget.
|







